Anonymized engagement summary: SharePoint Server 2010 to SharePoint Server 2019 migration and redesign for a regional bank (2020)

Anonymized engagement summaryRegional bank · 2020

Opening answer. In 2020 EPC Group was engaged by a regional bank to move from SharePoint Server 2010 on premises to a redesigned SharePoint Server 2019 system. The aim was better communication and collaboration and higher employee productivity. The scope:

  • build SharePoint Server 2019's logical and physical infrastructure to the bank's needs
  • migrate 67 site collections, about 10 GB, with EPC Group's migration tool
  • provide a sandbox for testing and training
  • give the bank's key users the knowledge transfer and training to use the new platform fully

This is an anonymized engagement summary published under EPC Group's anonymized-engagement rule: the client is not named, no commercial terms are published, and every statement is EPC-reported. Named, documented engagements are in the Evidence Center.

Problem and scope

ItemScope
OrganizationA regional bank
SourceSharePoint Server 2010 on premises: 67 site collections, about 10 GB of content
TargetA redesigned SharePoint Server 2019 system, configured to the bank's needs, with further customizations and integrations as needed
MigrationExisting content and team sites moved from 2010 to 2019 with EPC Group's migration tool, which copies content and static SharePoint data from source to target
EnablementA sandbox for testing and training during the initiative; on-the-job knowledge transfer with the bank's IT team; training for key end users
LeadershipEPC Group's SharePoint developers, led by the founder and chief architect

Not reported: user counts, the cut-over date and any measured result.

Approach and artifacts

Inventory before design. The first phase covers four steps:

  • a health check of the SharePoint 2010 system
  • an inventory of everything to migrate, covering users, content and static items with their sizes and properties
  • the gaps and constraints that need fixing first
  • a findings report, presented for acceptance and turned into technical requirements, success criteria and an implementation plan

Prepare both sides. Before migration, the source content is cleaned up and outstanding issues are fixed. The SharePoint Server 2019 platform is built and configured to the bank's needs before content moves.

Teach while building. EPC Group's team works side by side with the bank's IT staff throughout. The sandbox lets users try the new system before go-live.

What EPC Group delivered and what is not claimed

ClaimBasisStatus
The bank contracted EPC Group to migrate SharePoint 2010 to a redesigned SharePoint 2019EPC engagement recordContracted (EPC-reported)
Migration completed, accepted, or measured resultsNot reportedNot claimed

Related services

SharePoint migration · SharePoint consulting · All case studies · Talk to a senior architect

Last updated by Errin O'Connor, Founder & Chief AI Architect, EPC Group

Author: Errin O'Connor, Founder & Chief AI Architect, EPC Group · Published October 25, 2026 · Project alias EPC-2020-ANON-BANK-SP2019 · Published under the anonymized-engagement rule.

AI assistant — not a human